Rob Watson, Vessel Scanning, Ship Scanning, BoatBuilder, Yacht Designer, Custom Yacht Design, PassageMaker, Passage Maker, Custom Yacht Design, Custom Design, Boats, Marine Designer, AutoCAD, Drafting, Lofting, Deck Plans, Part Drawings, Mechanical Animations, Processes, Safety and Training.© 2006 - C.R. Watson, Watson Enterprises
HOME

PROJECT MANAGEMENT

CUSTOM DESIGNS

EXAMPLES

 CONTACT US

 
 
PROJECT HISTORY
 
A TWO YEAR PROJECT FOR THE MARINE RELATED INDUSTRY (Please note: This is a work in progress. Comments are being added periodically.)
by: Rob Watson
updated: April 17, 2010

After making several marketing video productions for Thrustmaster of Texas, Inc.it became apparent that there was quite a bit of work to do for this one customer. Thrustmaster was growing by leaps and bounds. With an ever expanding global customer base and plans to open new offices around the world, the products were becoming larger and more sophisticated. Meanwhile the demand for broader marketing materials was matching that growth. Seizing the opportunity to become involved in a large project Rob Watson approached the owner of Thrustmaster with an offer to work full time. With a handshake and a nod the deal was struck. Rob was hired as a Project Manager which left the door open to just about any assignment deemed important by the owner.

Whether the project is landlocked such as this new facility, or a new vessel or reconstruction, Project Management principles take the same amount of diligence. While a degree in industrial engineering is helpful, multi-faceted experience can work to the projects favor just as well. Especially when that experience leads to understanding the necessities of each aspect of the project. For example, the installment of three new CNC machining centers requires more than just the footprint of the machine. It helps to know what sort of tooling and periphery workspace is required.

Rob's first project was to manage the delivery of Thrustmaster's new headquarters. The worlds largest dedicated thruster factory! Seventeen acres of manufacturing and office space, the installation of new CNC machines, cranes up to 100 tons, and a 15 million gallon test pond. This project would begin during the planning stage and follow though for two years to include every aspect from permitting, through construction, the inclusion of a completely self-contained water well, septic, and fire suppression system. That's, right. Thrustmaster also provides water through it's own wells, has it's own septic system, and also provides it's own fire protection. Below is an account of some of the highlights of the project.

 
 

You can't start any project without the right people. This is my trusty "side-kick". This is the guy that makes sure that the people on site are doing what they say they are. Be it at 3:00 am, on the weekend, or until "dark-thirty", hiring Roy Weisinger was one of the best moves we made. With over 50 years experience Roy proved to be a major asset as contractors sought his advice and site workers took his direction without complaint.

Here Roy has mounted a digital camera on the end of a PVC pipe. He's set the timer on the camera to snap after 10 seconds. Inserting the camera down into the boring holes he took pictures of the conditions near the bottom where light wouldn't shine so he could insure that the footer had been reamed properly.

  When I took over the project the entire 54 acre tract was wooded pasture. Cows ran the property and the landscape ranged from swamp to gullies. The carcass of a dead calf and mother cow led me into a wooded area where the long dried bones of other dead cows was scattered throughout the thick underbrush. Surely the surveyors had seen these bones but no one seemed interested. My interest was that as this property had long been used for agriculture purposes for running cattle I didn't want someone to later say that we had harmed their cows. (Actual picture not shown because it would upset my granddaughter.)

During my original review of the property I found evidence of an old telephone line. The easement only ran a few hundred feet and then terminated near the middle of the property. Practicing "due diligence" and just for good laugh I called the Operator and asked for "Enterprise 9800." (For those too young to remember, phone numbers were typically spelled out so they would be easy to remember. Our home phone back then was "Rockwell 9..."

We did eventually get a release of the easement for legal purposes because it continually showed up on the plats causing problems with getting later easements that were necessary for our electrical service.

 

Proving that you have to keep an eye on everybody. I had ordered all 54 acres completely cleared. As the excavators and bulldozers were nearing the end of their clearing stages this one tree stood out day after day. I asked the operators why it was still there. Answer, "We didn't want to clear it because it "spoke to us."

My answer was to ask, "When it spoke to you, did it offer to sign the check for your services?" Needless to say the tree was gone the next day.

  The property had been surveyed a few years earlier but I considered it my responsibility to know every inch of this project. Using the survey map I walked to every marker. Once found I placed my own marker and tape so that I would know and could be confident in pointing out where the property lines were. This helped tremendously as both County and State inspectors and officials came to the site later in the project to determine our status of construction and to fulfill their roles.
   With the land cleared we held a ground-breaking ceremony. Not once, but twice. The first was for county dignitaries and longstanding customers.
   The second was for the employees whom the owner attributes much of his success. (Who wasn't in this picture? As a matter of fact, who wasn't in almost every picture? Your truly. I was the one taking the pictures.)

With the property finally clean the back-hoe operator covers the fire pit.

Picking a location where no buildings would be built a deep pit was dug. During the clearing process trees and brush were piled for several weeks to dry out. Under coverage of a county burn permit the brush was burned in the pit under controlled conditions.

Here the property is finally cleared and ready to begin construction. During the process of clearing and making the ground ready there were many meetings and details to attend. Working with the Civil Engineers, Architects, banking officers, nearby property owners, and MUD (Municipal Utility District) officers were just a few. Not included in this summary is that the center acreage was part of a TCEQ cleanup which affected every aspect of this project. While the details would make for good reading they cannot be disclosed for obvious reasons.
  After all permits and plans have been satisfied with the county the laying of storm sewer is usually a hidden process. I say "hidden" because folks passing the site don't see the workers. They are down in the holes. There were quite a few times that someone at management level would comment that nothing was going on at the site. A LOT was going on, they just couldn't see it.
As a fisherman I say, "Pollute it here..., eat it there. A good reason to be diligent." This was just the first of half a dozen truckloads of underground conduit and junction boxes that are typically buried below any commercial buildings or parking lots. A site that was once capable of absorbing rainwater now has to shed that water and do it so that it does not create flooding conditions elsewhere around the property. The amount of water has to be calculated and then diverted to receiving areas of run off. Typically ditches or other forms of drainage systems that are all part of the regional flood control program. During and after installation the project is monitored by county officials to insure that the plans are followed to a T. In addition to run off, the plans must be reviewed to insure that there are no avenues for pollutants to migrate from the manufacturing process into the water courses since this water ends up in our rivers and bays.
In the form of a very basic explanation, one aspect that we don't typically think about is that the parking lot has to be designed so that run off is equal in all directions. Based on the amount of water expected from a rain event and then starting at where the water enters the drain the remaining components must be positioned so that the last place the water leaves at the last drain is at or lower than where it started from. Otherwise, water backs up into the drain causing stagnation and foul smells to constantly waft from the holes.
Because this factory building and office is so large each column requires a pier with footer. These holes and the concrete are typically drilled down to "load bearing" surfaces. Sometimes it is rock. Other times (as in our case) it is packed clay down between 10 - 14 feet.

To make the process more efficient three crews work together. Referring to the plans the drilling crew first digs the hole using an auger. They then move to the next hole while the bell crew reams the bell at the bottom of the hole. Once that is done they move to the next hole location and the concrete crew follows immediately behind. In this shot the belling crew is barely clear before the concrete truck is positioned to start pouring.

Another aspect of this level of new construction as might be seen later is represented by this picture. Any time you move dirt you have one of two options. (1) reuse it, or, (2) relocate it.

Having preplanned the location of heavy factory machines the workers begin digging out squares where thicker concrete will be poured. This is a monolithic slab where the thicker concrete sections are poured at the same time as the floor. The thicker concrete provides much needed support for the heavy machines that would break the standard concrete floor. It also allows anchor bolts to be drilled and firmly seated so that the machines do not "walk" as might be caused by machining vibrations.

These particular monolithic pours are much shallower and very different from the machine foundations shown later.

Once the monolithic slab holes are dug the rebar has to be specially fitted to include the additional concrete. It appears obvious that drilling into the concrete for the purpose of installing anchor bolts would be hampered by all the steel.

The general contractor decided to pour segments lengthwise rather than across the shorter width. In the beginning I didn't see where it made any difference so I observed the process very closely thinking I was going to learn something new. In the end, I still say it didn't make any difference.

So, in the terms of project management this is one of those times when you simply don't make an issue of it and let the GC work the way they want to.

It's 3:30 in the morning. As I said previously Roy Weisinger is on scene ahead of the concrete trucks. They are ready their pour - but, within minutes Roy has a sample of the concrete and immediately calls a halt.

These chunks of concrete rip-rap were in the mix. This just proves why you have someone on site, and why you take samples of EVERY load run.

In addition to the concerns of underground runs for your own site services you have to make certain to include those services that come from outside resources such as the Electric Company, the Telephone Company, the Gas Company, and Water/Sewer, etc. The reason I make this point is that you might or MIGHT NOT have been involved in the planning work of a particular utility service provider. They might THINK that you were involved and aware.

Point: As the project manager you have to make certain that YOU are in charge of every service run, that you know where they are coming from and where they are going, and how they plan to get there. You cannot leave it to chance nor can you leave it to them to figure out and do as they please.

Part of this project included the development of Thrustmaster Drive. First slated to be a county road along private property with an easement that would have provided a payback, the city and county planners both eventually got involved. What started as a simple road to allow access with large truck traffic turned into a major county road with. I addition there was another intersecting road that went nowhere except to split the property into two sections. Literally, it was only planned for the future and did nothing for the next 20 years. The owner then decided to pay for it himself and in exchange, had the road named according to his desire.
Hurricane Rita heads for the Gulf Coast. Needless to say construction is put on hold as workers from around the Houston area turn their attention to taking care of family and homes. Our family covers from Orange County to Harris County so regardless of where the storm hits, we are all going to be affected. And we were. But, thanks to the Lord that no one was hurt we all pulled through and within a couple of weeks were back up and running full steam.
Thrustmaster decision makers pull in a MEGA-GENERATOR and connect up to the main power. Manufacturing keeps running for days as this monster pumped out the kW's. Those tanks in front are diesel fuel which was consumed at about 250 gallons per day of operation.
Finally, the first steel is erected! As you can see in this photo the first column on the north-east corner goes up without much fanfare. If you look closely you can see that there is a lot of concrete on the ground.
With the foundation established the frame structure begins to move very quickly as the frames and beams were all pre-fabricated to fit. It is far from an erector set which has holes strategically placed to allow for a variety of assemblies. In this case if a set of holes are off my mere inches there is going to be trouble down the road. Either the holes have to be fixed on site, or the holes have to be fixed on site. In other words, when you start assembling this kind of structure there isn't much choice.
Out front the factory office building continues at a much slower pace. In part because the same workers and equipment needed for the office are working on the factory. Part two, because the office building is far more complex in the amount of "layers" it will take to build it.
Finally! The steel for the office building arrives. In this photo I pulled one of my no-no's and accidentally got my shadow in the picture. The four truckloads were the first round of three more deliveries that would come over the next two weeks. This photo was taken on Jan 15, 2009.
Second no-no. Did it again! Or did I? One "tell" is the date. I don't include the date on my photos because it is in the hidden data. This photo was taken by Roy. This photo can also indicate the approximate time. If you know that (1) Roy is facing west north west, (2) the sun is rising directly behind him, and (3) the long cast of his shadow you can tell that the sun is just coming over the horizon so it's very early in the morning. This is the condition of the site on Jan 21, 2009.
  On Jan 21, 2009 you can see progress of the factory.  More importantly for us, after the hurricane our electrical service was put on the back burner by Centerpoint as their crews were tied up repairing downed and damaged power lines around Harris and Ft. Bend counties. This photo shows that by mid January we have the poles and hardware in place, however, the service is still not ready. Throughout this time the general contractor is working with one single electrical service point between the buildings. The extension cords are getting too long so generators are deployed to supplement the lack of electrical services.
A concrete pump truck moves into position. In the background you can see that the building is coming together. This is on February 12, 2009 and the second floor is getting ready to be poured. One thing about this project is that the General Contractor kept things moving. When we couldn't work on the building, or he had an excess of manpower he put them to pouring or getting the site ready for parking lot pours.
Finally, Centerpoint arrives with the the main factory transformer. These transformers have to be ordered 6-9 months in advance so when you start such a project you want to determine your anticipated power usage and get the electrical provider on the line early and get this one item ordered as early as possible. Another early stage item is to understand the requirements for the pad, and for the barriers. Here you can see that we've already set inserts for the barriers so that we could pour the parking lot. These barriers would be inserted into the sleeves and cemented in later.
Yours truly standing with the pump truck operator as we pour black concrete on the second floor.
The factory is progressing quick although we would like to have made it much faster. We were working against a production deadline as well as a construction loan deadline and regardless of the affects of the hurricane, we needed to be in and cutting steel within the next 4 months.
Timed with completing the roof the first phase of building a foundation for a CNC Machining Center is built. The leave-out and resulting excavation for this project was larger than my first home.
Workers in this scene give a better perspective of the depth of this tiered hole. The worker standing at the bottom represents where a solid concrete monolith will be poured. This will serve as the foundation for the machine.
The form is being set for the first pour. That block will be isolated by a 3/4" fiber shell and the next layer poured. Then a third until the foundation is completed by the "apron".
A contract sign painter outlines the unique Thrustmaster logo. Not such an easy task on a corrugated wall.
The Thrustmaster logo is finished. It was considered that we paint that logo onto the roof so the next time a satellite passes to take a photo and replace those on Google (TM) and such sites the building could be seen from space.
Obviously, in building construction the project is the entire building, not just one floor. There is no such thing as any single floor affecting only itself. Likewise, the elevator shaft, AC ducting, chases for wiring and plumbing, and stairwells are examples of the kinds of "multiple floor high impact" issues construction projects face. Our design on this elevator shaft is to also include the half-round stairwell between floors. This minimizes the amount of space needing to be dedicated to both since they share the same opening and footprint.
Barely down 8 feet and we are seeing water in the clay. Our boring surveys showed something else that made the steel pipe in the background necessary for setting the piers. Throughout the area there were layers of sand and silt that would collapse or sluff off before we could pour the concrete. In this case the sleeve would be inserted into the hole before the walls sluffed off. This allowed re-bar to be inserted without worrying about hitting the walls. Concrete would then be pumped into the sleeve as it was withdrawn from the hole allowing that the pressure of the concrete would push against the looser sand and silt while it set and prevent the walls from collapsing.
 
 

Disclaimer
 
© 1997-2010 c.r. watson - all rights reserved
The use of any trademarks, trademarked names, and/or copyrighted information is stated as a fact of record and is not
intended to imply endorsement of any kind. The use of any pictures, writings, or materials from this site without
express written consent of Charles R. Watson dba Watson Enterprises aka MarineImaging.com is forbidden.